Susitna Project supplemental report, low Watana Dam RCC concept cost evaluation : final /
For the Watana Dam on the Susitna River, the option of a roller-compacted concrete (RCC) dam has been suggested for consideration. The consultants developed a conceptual design and performed concept level cost estimates for a RCC dam at the Watana and Devil Canyon sites as described in the report &q...
Saved in:
Alternate Title: | Susitna Project supplemental report, low Watana Dam roller compacted concrete concept cost evaluation : final Supplemental report - low Watana RCC concept |
---|---|
Corporate Contributor(s): | R & M Consultants. Hatch Associates Consultants, Inc. Jack Linard Consulting. Alaska Energy Authority. |
Publisher: | Alaska Energy Authority, |
Report Numbers: | SuWa 216 |
Series: | Susitna-Watana Hydroelectric Project document ;
no. 216. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 03142cam a2200529Ia 4500 | ||
---|---|---|---|
001 | 2040382 | ||
003 | SIRSI | ||
005 | 20140620043903.0 | ||
007 | ta | ||
007 | cr cn||||a|||| | ||
008 | 140619s2010 akube b s000 0 eng d | ||
040 | |a RLA |c RLA |d RLA | ||
035 | |a (OCoLC)881507175 | ||
043 | |a n-us-ak | ||
050 | 4 | |a TK1425.S8 |b S92 no. 216 | |
088 | |a SuWa 216 | ||
049 | |a RLAA | ||
245 | 0 | 0 | |a Susitna Project supplemental report, low Watana Dam RCC concept cost evaluation : |b final / |c prepared by R & M Consultants, Hatch Associates Consultants, Jack Linard Consulting. |
246 | 3 | |a Susitna Project supplemental report, low Watana Dam roller compacted concrete concept cost evaluation : |b final | |
246 | 1 | 7 | |a Supplemental report - low Watana RCC concept |
260 | |a [Anchorage : |b Alaska Energy Authority, |c 2010] | ||
300 | |a iii, 21, [22], 61 p. : |b 2 maps, 13 plans ; |c 28 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
490 | 1 | |a Susitna-Watana Hydroelectric Project document ; |v no. 216 | |
500 | |a "November 29, 2010." | ||
500 | |a ARLIS assigned report number: SuWa 216. | ||
500 | |a Posted on the Alaska Energy Authority's "Railbelt large hydro reports" webpage; available as of June 16, 2014. | ||
530 | |a Available also in electronic format on the Internet. | ||
610 | 2 | 0 | |a Susitna-Watana Hydroelectric Project. |
520 | |a For the Watana Dam on the Susitna River, the option of a roller-compacted concrete (RCC) dam has been suggested for consideration. The consultants developed a conceptual design and performed concept level cost estimates for a RCC dam at the Watana and Devil Canyon sites as described in the report "Susitna RCC dam cost evaluation : final" dated November 16, 2009. This report is considered an addendum that that report. In addition, this report explores the advantages and disadvantages of an underground versus surface powerhouse, and transportation options utilizing updated information on railroad costs in conjunction with "rail only" surface transport to the project. | ||
505 | 0 | |a Executive summary -- Introduction -- Project layout -- Project access issues -- Cost estimates -- Project schedule -- Figures -- appendix A. Breakdown of unit cost analysis for RCC -- appendix B. Detailed construction cost. | |
504 | |a Includes bibliographical references (first sequence, p. 21). | ||
650 | 0 | |a Dams |x Design and construction |x Estimates |z Alaska |z Susitna River. | |
650 | 0 | |a Dams |z Alaska |z Susitna River |x Design and construction. | |
650 | 0 | |a Roller compacted concrete. | |
710 | 2 | |a R & M Consultants. | |
710 | 2 | |a Hatch Associates Consultants, Inc. | |
710 | 2 | |a Jack Linard Consulting. | |
710 | 2 | |a Alaska Energy Authority. | |
772 | 0 | |7 unam |t Susitna RCC dam cost evaluation. |d [Anchorage : Alaska Energy Authority, 2009] |r SuWa 197 |w (OCoLC)528992984 | |
830 | 0 | |a Susitna-Watana Hydroelectric Project document ; |v no. 216. | |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna2/2/SuWa216.pdf |z ARLIS Document Server |
901 | |a 3755 |c orig | ||
596 | |a 9 10 | ||
098 | |a SuWa 00216 |