Backup Book E, Devil Canyon - concrete costs.
A collection of hand-completed worksheets (called 'Calculations' or 'Estimate work sheet') from Acres American Incorporated regarding estimated costs for the planned arch Devil Canyon Dam, part of the Susitna Hydroelectric Project.
Saved in:
Alternate Title: | Book E. Backup Book E, Devil Canyon - concrete costs. Title entered in the Susitna Hydroelectric Project document index as: Devil Canyon concrete works, Book E, Task 9 - Group 12 Title on label on binder cover (difficult to read due to poor reproduction): Task 9 - Group 12, Book E, Devil Canyon concrete works Caption title on page 1 (table of contents page): Unit prices - backup calculations, Devil Canyon, concrete works (E). Unit prices - backup calculations, Devil Canyon, concrete works |
---|---|
Corporate Contributor(s): | Acres American Incorporated. HARZA-EBASCO Susitna Joint Venture. |
Publisher: | Acres American Incorporated, |
Report Numbers: | APA 255 |
Series: | Document (Susitna Hydroelectric Project) ;
no. 255. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
Contents:
- Summary
- Structures
- Summary
- Powerhouse
- Transformer gallery
- Auxiliary spillway
- Emergency spillway
- Surge chamber
- Intake
- Bus tunnels & shafts
- Summary
- Division tunnel
- Tailrace tunnel
- Main access tunnel
- Grout galleries
- Cable shaft
- Access shaft
- Penstocks
- Forming crews
- Placing crews
- Supply of concrete
- Concrete production
- Cement
- Coarse aggregate
- Fine aggregate
- Supply & install rebar.