Susitna Hydroelectric Project, Watana, concrete arch dam.
Contains calculations. Pages 2-10 contain estimated costs of building the Watana dam. Pages 11-13 comprise two memoranda on dam design (reinforcing steel, stell mesh, underground rockbolts, etc.) and concrete mix design.
Saved in:
Alternate Title: | Susitna Hydroelectric Project, Concrete dam at Watana, estimate based on scheme "2A" Title in the Susitna Hydroelectric Project document index: Project services, estimating Group 6, Watana concrete arch dam, calculations |
---|---|
Corporate Contributor(s): | Acres American Incorporated. |
Publisher: | [Acres American Incorporated], |
Report Numbers: | APA 93 |
Series: | Document (Susitna Hydroelectric Project) ;
no. 93. |
Subjects: | |
Online Access: | Link to Full Text Link to Full Text |
Library Holdings: | Print Versions |
Summary: | Contains calculations. Pages 2-10 contain estimated costs of building the Watana dam. Pages 11-13 comprise two memoranda on dam design (reinforcing steel, stell mesh, underground rockbolts, etc.) and concrete mix design. |
---|---|
Physical Description: | 13 p. ; 28 cm. |
Notes: | Issued by Acres American Incorporated according to the Susitna Hydroelectric Project document index. "October 1981." |