AGDC says it needs until June to answer more of FERC's engineering questions
The Alaska Gasline Development Corp. (AGDC) told federal regulators it will be late June 2019 before the project team can provide all the detailed engineering data requested in December 2018 for the proposed Alaska LNG Project’s gas treatment plant at Prudhoe Bay and gas liquefaction plant in Nikisk...
Saved in:
Main Author: | |
---|---|
Document Type: | Press release |
Publisher: | Alaska Resources Library and Information Services (ARLIS) |
Date: | January 16, 2019 |
Series: | Alaska LNG Project updates
|
Subjects: | |
Online Access: | View Full Text View Full Text |
Library Holdings: | Print Versions |
LEADER | 02151cam a22003733 4500 | ||
---|---|---|---|
001 | 5081911 | ||
003 | SIRSI | ||
008 | 190116s2019 o 000 0 eng u | ||
100 | 1 | |a Persily, Larry | |
245 | 1 | 0 | |a AGDC says it needs until June to answer more of FERC's engineering questions |
260 | |a Alaska Resources Library and Information Services (ARLIS) | ||
264 | |a 20190116 | ||
300 | |a 3 pages | ||
380 | |a Press release | ||
490 | |a Alaska LNG Project updates | ||
518 | |a January 16, 2019 | ||
546 | |a English | ||
500 | |a This update is provided to keep the public informed about the Alaska LNG Project. | ||
520 | |a The Alaska Gasline Development Corp. (AGDC) told federal regulators it will be late June 2019 before the project team can provide all the detailed engineering data requested in December 2018 for the proposed Alaska LNG Project’s gas treatment plant at Prudhoe Bay and gas liquefaction plant in Nikiski. Simultaneously, the Office of Energy Projects issued an additional 20 pages of detailed engineering questions for AGDC. Questions deal with the Cook Inlet crossing, relocation of existing pipelines and roadway, types of piles for foundations, and earthquake faults among many other engineering, design, and safety issues. Meanwhile, AGDC tackles marketing and its own budget concerns as it experiences changes during the transition to a new state governor. | ||
610 | 2 | |a Alaska LNG Project | |
610 | 2 | |a Alaska Gasline Development Corporation (AGDC) | |
610 | 2 | |a Federal Energy Regulatory Commission (FERC) | |
610 | 2 | |a Federal Energy Regulatory Commission. Office of Energy Projects | |
653 | |a Request for information | ||
653 | |a Engineering | ||
653 | |a Hazard mitigation | ||
600 | 1 | |a Dubler, Joe | |
600 | 1 | |a Meyer, Keith | |
690 | |a PF-AKGOV | ||
690 | |a PF-CONS | ||
856 | 4 | 0 | |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_Persily-2019_AGDC_SaysItNeedsUntilJuneToAnswer.pdf |3 Direct link to this update |
856 | 4 | 2 | |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_KPB_AK_LNG_ProjectUpdate.html |3 Website listing all Project updates |
901 | |a ARLIS |c orig 201901 | ||
596 | |a 10 |