State will submit rest of Cook Inlet crossing information by September

The Alaska LNG Project team will submit details on the Cook Inlet pipeline crossing in September 2019. The current plan is to trench and bury the 42-inch diameter pipe nearshore and to lay it on the seafloor in between coated with concrete. The Federal Energy Regulatory Commission (FERC) is requesti...

Full description

Saved in:
Bibliographic Details
Main Author: Persily, Larry
Document Type: Press release
Publisher:Alaska Resources Library and Information Services (ARLIS)
Date:December 18, 2018
Series:Alaska LNG Project updates
Subjects:
Online Access:View Full Text
View Full Text
Library Holdings:Print Versions
LEADER 02627cam a22005173 4500
001 5076783
003 SIRSI
008 181218s2018 o 000 0 eng u
100 1 |a Persily, Larry 
245 1 0 |a State will submit rest of Cook Inlet crossing information by September 
260 |a Alaska Resources Library and Information Services (ARLIS) 
264 |a 20181218 
300 |a 4 pages 
380 |a Press release 
490 |a Alaska LNG Project updates 
518 |a December 18, 2018 
546 |a English 
500 |a This update is provided to keep the public informed about the Alaska LNG Project. 
520 |a The Alaska LNG Project team will submit details on the Cook Inlet pipeline crossing in September 2019. The current plan is to trench and bury the 42-inch diameter pipe nearshore and to lay it on the seafloor in between coated with concrete. The Federal Energy Regulatory Commission (FERC) is requesting answers to detailed questions on this proposed crossing before it releases its final environmental impact statement. The Alaska Gasline Development Corporation released information trench crossings at water crossings and about trenchless river crossings for some rivers using direct microtunneling at permafrost locations (Middle Fork Koyukuk, Yukon, Tanana, and Deshka). Moreover, the U.S. Fish and Wildlife Service has noted concerns with migratory birds. Also, the FERC docket this month contains a filing submitted by 18 property owners at Boulder Point concerned about the pipeline location in Nikiski and the dam at Suneva Lake. 
610 2 |a Alaska LNG Project 
610 2 |a Federal Energy Regulatory Commission (FERC) 
610 2 |a U.S. Fish and Wildlife Service (FWS) 
653 |a Birds 
653 |a Buried pipelines 
653 |a Cook Inlet crossing 
653 |a Microtunneling 
653 |a Landowners 
653 |a Open-cut trenching 
653 |a Permafrost 
653 |a Request for information 
653 |a Seafloor 
653 |a Stream crossings 
653 |a Waterbodies 
651 |a Boulder Point 
651 |a Cook Inlet 
651 |a Deshka River 
651 |a Middle Fork Koyukuk River 
651 |a Tanana River 
651 |a Suneva Lake 
651 |a Yukon River 
690 |a PF-AKGOV 
690 |a PF-ENVI 
856 4 0 |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_Persily-2018_StateWillSubmitCookInletCrossingInfo.pdf  |3 Direct link to this update 
856 4 2 |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_KPB_AK_LNG_ProjectUpdate.html  |3 Website listing all Project updates 
901 |a ARLIS  |c orig 201812 
596 |a 10