Susitna-Watana Hydroelectric Project, FERC Project no. 14241-000 ; Second set of 2014 technical memoranda for Initial Study Plan meetings.

This cover letter accompanies seven technical memoranda that were written during the 2014 study season of the Susitna-Watana Hydroelectric Project and submitted by the Alaska Energy Authority to the Federal Energy Regulatory Commission as a group filing. These documents all deal with the Susitna Riv...

Full description

Saved in:
Bibliographic Details
Alternate Title:Second set of 2014 technical memoranda for Initial Study Plan meetings

Title on Project's Document webpage: September 26 technical memoranda cover letter
Main Author: Dyok, Wayne,
Additional Author(s):Bose, Kimberly D.,
Corporate Contributor(s):Alaska Energy Authority.

Susitna-Watana Hydroelectric Project.
Publisher:Alaska Energy Authority,
Report Numbers:SuWa 239
Series:Susitna-Watana Hydroelectric Project document ; no. 239.
Subjects:
Online Access:Link to Full Text
Link to Full Text
Library Holdings:Print Versions
Description
Summary:This cover letter accompanies seven technical memoranda that were written during the 2014 study season of the Susitna-Watana Hydroelectric Project and submitted by the Alaska Energy Authority to the Federal Energy Regulatory Commission as a group filing. These documents all deal with the Susitna River, most of which deals with geomorphology and the rest with beluga whale prey, river productivity, and biotic communities in the river.
Physical Description:3 p. ; 28 cm.
Notes:Title from subject line.

"September 26, 2014."

ARLIS assigned report number: SuWa 239.

Letter of transmittal to Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, from Wayne Dyok, Project Manager, Alaska Energy Authority, dated September 26, 2014.

Each attachment to this document is cataloged separately in order to provide details on those portions. These materials are assigned numbers SuWa 240 through 246.

This cover letter serves as a filing document for seven technical memoranda generated during the 2014 study season of the Susitna-Watana Hydroelectric Project, each listed in the letter as attachments. The cover letter and the attached reports were submitted to FERC on September 26, 2014 (numbered SuWa 239-246).
Report Type:September 26, 2014 technical memorandum filings.

Technical memorandum.
Related Titles:Accompanied by (manifestation): Geomorphology study (Study 6.5), updated mapping of aquatic macrohabitat types in the middle Susitna River segment from 1980s and current aerials, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 240 SuWa 240 Attachment A to this letter.

Accompanied by (manifestation): Geomorphology study (Study 6.5), mapping of geomorphic features and turnover within the middle and lower Susitna River segments from 1950s, 1980s, and current aerials, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 241 SuWa 241 Attachment B to this letter.

Accompanied by (manifestation): Fluvial geomorphology modeling below Watana Dam study (Study 6.6), decision point on fluvial geomorphology modeling of the Susitna River below PRM 29.9, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 242 SuWa 242 Attachment C to this letter.

Accompanied by (manifestation): River productivity study (Study 9.8), 2014 field season river productivity progress report, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 246 SuWa 246 Attachment G to this letter.

Accompanied by (manifestation): Fluvial geomorphology modeling below Watana Dam study (Study 6.6), winter sampling of main channel bed material, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 243 SuWa 243 Attachment D to this letter.

Accompanied by (manifestation): Cook Inlet beluga whale study (Study 9.17), 2014 Cook Inlet beluga whale prey study implementation, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 244 SuWa 244 Attachment E to this letter.

Accompanied by (manifestation): River productivity study (Study 9.8), 2013 initial river productivity results, technical memorandum. [Anchorage : Alaska Energy Authority, 2014] Susitna-Watana Hydroelectric Project document ; no. 245 SuWa 245 Attachment F to this letter.