Preliminary report on the continuation of feasibility studies : submitted to the Alaska Legislature and Governor Hammond /

An overview of the tentative findings of the Alaska Power Authority regarding the advisability of developing the hydropower potential of the Susitna River to meet the energy needs of Alaska's "railbelt" region. Report includes load requirements, seismic risks, environmental implicatio...

Full description

Saved in:
Bibliographic Details
Alternate Title:Susitna Hydroelectric Project, preliminary report on the continuation of feasibility studies : submitted to the Alaska Legislature and Governor Hammond

Susitna Hydroelectric Project mid report to Governor Jay S. Hammond and the Legislature of the State of Alaska
Corporate Contributor(s):Alaska Power Authority.
Publisher:Alaska Power Authority,
Report Numbers:APA 2930

SUS 64
Series:Document (Susitna Hydroelectric Project) ; no. 2930.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
Contents:
  • Purpose
  • Report format
  • Introduction
  • Decison criteria
  • Load requirements
  • Seismic risks
  • Environmental implications
  • Economic feasibility
  • Project financing
  • Permit requirements and construction schedule
  • Public participation
  • Land status and native involvement.