Susitna Hydroelectric Project feasibility report. Supplement /
This supplemental report is intended to provide an update of information through January 1983 as a supplement to the feasibility report for the Susitna Hydroelectric Project, which was issed March 15, 1982.
Saved in:
Corporate Contributor(s): | Susitna Hydroelectric Project. Acres American Incorporated, Alaska Power Authority, |
---|---|
Publisher: | Alaska Power Authority, |
Report Numbers: | APA 504 APA 505 APA 506 APA 1619 APA 1620 |
Edition: | [Final]. |
Series: | Document (Susitna Hydroelectric Project) ;
no. 504-506. Document (Susitna Hydroelectric Project) ; no. 1619-1620. |
Subjects: | |
Online Access: | Link to Full Text Link to Full Text Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 03728cam a2200721Ia 4500 | ||
---|---|---|---|
001 | 1645561 | ||
003 | SIRSI | ||
005 | 20160524010051.0 | ||
007 | ta | ||
007 | cr bn||||a|||| | ||
008 | 850208s1983 akuabe bt s000 0 eng d | ||
040 | |a UDA |b eng |c UDA |d UAB |d RLA |d OCLCQ |d RLA |d OCLCF |d OCLCQ |d RLA |d OCL |d RLA | ||
035 | |a (OCoLC)11671715 | ||
043 | |a n-us-ak | ||
050 | 4 | |a TK1425.S8 |b A23 no. 504-505 | |
050 | 4 | |a TK1425.S8 |b F4372 1983 | |
088 | |a APA 504 | ||
088 | |a APA 505 | ||
088 | |a APA 506 | ||
088 | |a APA 1619 | ||
088 | |a APA 1620 | ||
049 | |a RLAA | ||
245 | 0 | 0 | |a Susitna Hydroelectric Project feasibility report. |p Supplement / |c prepared by Acres. |
250 | |a [Final]. | ||
260 | |a [Anchorage, Alaska] : |b Alaska Power Authority, |c [1983] | ||
300 | |a 2 volumes : |b illustrations, maps, plans ; |c 28-28 x 45 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
500 | |a "April 1983." | ||
510 | 3 | |a Assigned APA Document numbers 504 and 505 in Susitna Hydroelectric Project document index. Also assigned numbers 506, 1619 and 1620 (duplicate entries). | |
530 | |a Available also in electronic format on the Internet. | ||
520 | |a This supplemental report is intended to provide an update of information through January 1983 as a supplement to the feasibility report for the Susitna Hydroelectric Project, which was issed March 15, 1982. | ||
505 | 0 | 0 | |g v. 1. |t Engineering and economic aspects. |g (APA 504 or APA 1619) -- v. 2. |t Plates. |g (APA 505 or APA 506 or APA 1620). |
504 | |a Includes bibliographical references. | ||
610 | 2 | 0 | |a Susitna Hydroelectric Project |x Planning. |
650 | 0 | |a Dams |z Alaska |z Susitna River |x Planning. | |
650 | 0 | |a Hydroelectric power plants |z Alaska |z Susitna River |x Planning. | |
651 | 0 | |a Susitna River (Alaska) |x Power utilization |x Planning. | |
610 | 2 | 7 | |a Susitna Hydroelectric Project. |2 fast |0 (OCoLC)fst00592845 |
650 | 7 | |a Dams |x Planning |2 fast |0 (OCoLC)fst00887365 | |
650 | 7 | |a Hydroelectric power plants |x Planning. |2 fast |0 (OCoLC)fst00964961 | |
650 | 7 | |a Planning. |2 fast |0 (OCoLC)fst01065224 | |
650 | 7 | |a Water-power |x Planning. |2 fast |0 (OCoLC)fst01355318 | |
651 | 7 | |a Alaska |z Susitna River. |2 fast |0 (OCoLC)fst01246005 | |
710 | 2 | |a Susitna Hydroelectric Project. | |
710 | 2 | |a Acres American Incorporated, |e author. | |
710 | 2 | |a Alaska Power Authority, |e issuing body. | |
740 | 0 | 2 | |a Engineering and economic aspects. |
772 | 0 | |t Susitna Hydroelectric Project feasibility report. |b Final draft. |d [Anchorage, Alaska] : Alaska Power Authority, [1982] |r APA 174-182 |r SUS 38 |w (OCoLC)49820541 | |
787 | 0 | 8 | |i Revision of: |t Susitna Hydroelectric Project. Draft supplement to the feasibility report. |d [Anchorage, Alaska] : Alaska Power Authority, [1983] |n Only volume 1 is known. |r APA 614 |w (OCoLC)889526779 |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 504-506. | |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 1619-1620. | |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna/5/APA504.pdf |x This URL for the first volume is needed for image to display in the OPAC. |3 Direct link to Volume 1 (Engineering and economic aspects). |z ARLIS Document Server |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna/5/APA504.html |3 List of all volumes of this supplement. |z ARLIS Document Server |
856 | 4 | 2 | |u https://www.arlis.org/docs/vol1/Susitna/1/APA174.html |3 Link to the feasability report (final draft) and list of all documents related to it. |z ARLIS Document Server |
977 | |a o11671715 | ||
596 | |a 9 10 11 23 24 | ||
098 | |a APA 00504 | ||
098 | |a APA 00505 | ||
098 | |a APA 00506 | ||
098 | |a APA 01619 | ||
098 | |a APA 01620 |