Task 3, Hydrology. Processed climatic data. Volume 7, 0665 - Sherman Station, May 1982-September 1982 /

The Sherman Station began recording on May 15, 1982 after the Tyone River Station was relocated to become the Sherman Station. It is located at Susitna River Mile 129.5 downriver from Gold Creek.

Saved in:
Bibliographic Details
Alternate Title:Alaska Power Authority, Susitna Hydroelectric Project. Task 3, Hydrology. Processed climatic data. Volume 7, 0665 - Sherman Station, May 1982-September 1982

Processed climatic data. Volume 7, 0665 - Sherman Station, May 1982-September 1982

Processed climatic data, May 1982 thru September 1982. Volume 7, 0665 - Sherman Station

Susitna Hydroelectric Project. Processed climatic data, May 1982 thru September 1982. Volume 7, 0665 - Sherman Station

Task 3, Hydrology. Processed climatic data. October 1981 - September 1982

Alaska Power Authority, Susitna Hydroelectric Project. Task 3, Hydrology. Processed climatic data. October 1981 - September 1982
Corporate Contributor(s):Susitna Hydroelectric Project.

R & M Consultants,

Acres American Incorporated,

Alaska Power Authority,

HARZA-EBASCO Susitna Joint Venture.
Publisher:Alaska Power Authority,
Report Numbers:APA 48

APA 1739
Series:Document (Susitna Hydroelectric Project) ; no. 48.
Document (Susitna Hydroelectric Project) ; no. 1739.
Subjects:
Online Access:Link to Full Text
Link to Full Text
Library Holdings:Print Versions
Description
Summary:The Sherman Station began recording on May 15, 1982 after the Tyone River Station was relocated to become the Sherman Station. It is located at Susitna River Mile 129.5 downriver from Gold Creek.
Physical Description:iii, 8, [45] pages : illustrations, map ; 28 cm.
Notes:At head of title: Alaska Power Authority, Susitna Hydroelectric Project.

At head of cover title: Susitna Hydroelectric Project.

"Prepared for Acres American Incorporated."

Chiefly tables.

"December 1982."

Series statement from label on cover.