Task 6, Design development. Subtask 6.04, Closeout report. Evaluation of arch dam at Devil Canyon site /

"The scope of work under this subtask is essentially to review the designs previously undertaken not only for the Devil Canyon site but for comparable sites elsewhere in the world, and to consider the application of current state of the art design techniques for a dam at this site."--Leaf...

Full description

Saved in:
Bibliographic Details
Alternate Title:Susitna Hydroelectric Project. Task 6, Design development. Subtask 6.04, Closeout report. Evaluation of arch dam at Devil Canyon site

Subtask 6.04, Closeout report. Evaluation of arch dam at Devil Canyon site

Closeout report. Evaluation of arch dam at Devil Canyon site

Evaluation of arch dam at Devil Canyon site

Alaska Power Authority, Susitna Hydroelectric Project. Task 6, Design development. Subtask 6.04, Closeout report. Evaluation of arch dam at Devil Canyon site
Corporate Contributor(s):Acres American Incorporated.

Alaska Power Authority.
Publisher:Alaska Power Authority,
Report Numbers:APA 337

APA 1280

SUS 73
Series:Document (Susitna Hydroelectric Project) ; no. 337.
Document (Susitna Hydroelectric Project) ; no. 1280.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
LEADER 04348cam a2200781Ia 4500
001 250695
003 SIRSI
005 20140611044909.0
007 ta
007 he bmu|||bbca
007 cr bn||||a||||
008 860605s1982 akuabef b s000 0 eng d
040 |a AkU  |b eng  |c UAF  |d RLA  |d UAB  |d RLA  |d OCLCQ  |d RLA  |d OCLCF  |d RLA 
019 |a 70525441 
035 |a (OCoLC)42992300  |z (OCoLC)70525441 
043 |a n-us-ak 
050 4 |a TK1425.S8  |b A23 no. 337 
050 4 |a TC557.A4  |b S9744 1982 
088 |a APA 337 
088 |a APA 1280 
088 |a SUS 73 
049 |a RLAA 
245 0 0 |a Task 6, Design development.  |n Subtask 6.04,  |p Closeout report.  |p Evaluation of arch dam at Devil Canyon site /  |c prepared by Acres. 
246 3 |a Susitna Hydroelectric Project.  |n Task 6,  |p Design development.  |n Subtask 6.04,  |p Closeout report.  |p Evaluation of arch dam at Devil Canyon site 
246 3 0 |a Subtask 6.04, Closeout report.  |p Evaluation of arch dam at Devil Canyon site 
246 3 0 |a Closeout report.  |p Evaluation of arch dam at Devil Canyon site 
246 3 0 |a Evaluation of arch dam at Devil Canyon site 
246 3 |a Alaska Power Authority, Susitna Hydroelectric Project.  |n Task 6,  |p Design development.  |n Subtask 6.04,  |p Closeout report.  |p Evaluation of arch dam at Devil Canyon site 
260 |a [Anchorage, Alaska] :  |b Alaska Power Authority,  |c [1982] 
300 |a 58 p. in various pagings :  |b ill., 3 maps, plans ;  |c 28 cm. 
336 |a text  |b txt  |2 rdacontent 
337 |a unmediated  |b n  |2 rdamedia 
338 |a volume  |b nc  |2 rdacarrier 
490 1 |a [Document ;  |v no. 337, 1280] 
500 |a "March 1982." 
500 |a At head of title: Susitna Hydroelectric Project. 
500 |a At head of caption title on table of contents page: Alaska Power Authority, Susitna Hydroelectric Project. 
520 |a "The scope of work under this subtask is essentially to review the designs previously undertaken not only for the Devil Canyon site but for comparable sites elsewhere in the world, and to consider the application of current state of the art design techniques for a dam at this site."--Leaf 1-1. 
510 3 |a Assigned APA Document no. 337 in the Susitna Hydroelectric Project document index. Also assigned no. 1280 (duplicate entry). 
510 3 |a Assigned SUS document no. 73 in the Susitna Aquatic Impact Assessment Project bibliography. 
530 |a Available also in microfiche format; illustrations and plates are rearranged. 
530 |a Available also in electronic format on the Internet. 
505 0 |a Introduction -- Summary -- Scope -- Review of arch dam precedents -- Geotechnical considerations -- Seismic considerations -- Evaluation of previous designs -- Draft design -- Stress analysis -- Conclusions -- Bibliography -- appendix A. Stresses in thin arch dam -- appendix B. Stresses in gravity arch dam. 
504 |a Includes bibliographical references (p. [10-3]-[10-4]).  |b 19 
610 2 0 |a Susitna Hydroelectric Project. 
650 0 |a Arch dams  |z Alaska  |z Susitna River  |x Design and construction. 
650 0 |a Arch dams  |z Alaska  |z Devils Canyon  |x Design and construction. 
650 0 |a Arch dams  |x Earthquake effects  |z Alaska  |z Susitna River. 
650 7 |a Arch dams  |x Earthquake effects.  |2 fast  |0 (OCoLC)fst00812862 
650 0 |a Arch dams  |x Earthquake effects  |z Alaska  |z Devils Canyon. 
650 0 |a Gravity dams  |z Alaska  |z Devils Canyon  |x Design and construction. 
650 0 |a Hydroelectric power plants  |z Alaska  |z Devils Canyon  |x Planning. 
610 2 7 |a Susitna Hydroelectric Project.  |2 fast  |0 (OCoLC)fst00592845 
650 7 |a Arch dams  |x Design and construction.  |2 fast  |0 (OCoLC)fst00812861 
650 7 |a Gravity dams  |x Design and construction.  |2 fast  |0 (OCoLC)fst00946919 
650 7 |a Hydroelectric power plants  |x Planning.  |2 fast  |0 (OCoLC)fst00964961 
651 7 |a Alaska  |z Devils Canyon.  |2 fast  |0 (OCoLC)fst01870232 
651 7 |a Alaska  |z Susitna River.  |2 fast  |0 (OCoLC)fst01246005 
710 2 |a Acres American Incorporated. 
710 2 |a Alaska Power Authority. 
830 0 |a Document (Susitna Hydroelectric Project) ;  |v no. 337. 
830 0 |a Document (Susitna Hydroelectric Project) ;  |v no. 1280. 
856 4 1 |u https://www.arlis.org/docs/vol1/Susitna/3/APA337.pdf  |z ARLIS Document Server 
901 |a 3755 
596 |a 9 10 
098 |a SUS 00073 
098 |a APA 00337 
098 |a APA 01280