Preliminary working draft, access plan report, Susitna Hydroelectric Project /

Various access routes to the Devil Canyon Dam and Watana Dam sites are evaluated. Harza-Ebasco concludes that the either the North or Denali access plans is acceptable and that the Denali plan in preferred. The North plan (Plan 16) consists of a gravel road from the George Parks Highway at Hurricane...

Full description

Saved in:
Bibliographic Details
Alternate Title:Alaska Power Authority, Susitna Hydroelectric Project. Access plan report

Access plan report

Title on label on cover provided by Harza-Ebasco research team: APA, Susitna Hydroelectric Project, access plan report
Corporate Contributor(s):HARZA-EBASCO Susitna Joint Venture.

Alaska Power Authority.
Publisher:Harza-Ebasco Susitna Joint Venture,
Report Numbers:APA 500
Series:Document (Susitna Hydroelectric Project) ; no. 500.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
LEADER 02920cam a2200517Ia 4500
001 2055748
003 SIRSI
005 20140915130514.0
007 ta
007 cr bn||a||||||
008 140915s1983 akuab bt 000 0 eng d
040 |a RLA  |c RLA 
035 |a (OCoLC)890600160 
043 |a n-us-ak 
050 4 |a TK1425.S8  |b A23 no. 500 
088 |a APA 500 
245 0 0 |a Preliminary working draft, access plan report, Susitna Hydroelectric Project /  |c for Alaska Power Authority ; by Harza-Ebasco. 
246 1 4 |a Alaska Power Authority, Susitna Hydroelectric Project.  |p Access plan report 
246 3 0 |a Access plan report 
246 1 |i Title on label on cover provided by Harza-Ebasco research team:  |a APA, Susitna Hydroelectric Project, access plan report 
260 |a [Alaska?] :  |b Harza-Ebasco Susitna Joint Venture,  |c 1983. 
300 |a 183 p. in various pagings :  |b ill., maps ;  |c 28 cm. 
336 |a text  |b txt  |2 rdacontent 
337 |a unmediated  |b n  |2 rdamedia 
338 |a volume  |b nc  |2 rdacarrier 
490 1 |a Harza-Ebasco Susitna Joint Venture document ;  |v no. 500 
500 |a "1983." 
500 |a Series statement from label on cover. 
510 3 |a Assigned APA Document no. 500 in the Susitna Hydroelectric Project document index. 
530 |a Available also in electronic format on the Internet. 
520 |a Various access routes to the Devil Canyon Dam and Watana Dam sites are evaluated. Harza-Ebasco concludes that the either the North or Denali access plans is acceptable and that the Denali plan in preferred. The North plan (Plan 16) consists of a gravel road from the George Parks Highway at Hurricane along the north bank of the Susitna River to Watana with provisions for a future branch road to the Devil Canyon site. The Denali plan (Plan 18) consists of a railhead at Cantwell with a new access road leading south towards Watana from a point on the Denali Highway 21 miles east of Cantwell; the Devil Canyon Dam would be supported by a rail spur from Gold Creek; and a road would be constructed between the two sites for operational purposes. 
504 |a Includes bibliographical references. 
610 2 0 |a Susitna Hydroelectric Project  |x Planning. 
650 4 |a Access roads  |z Alaska  |z Susitna River Region. 
650 4 |a Dams  |x Access roads  |z Alaska  |z Susitna River Region. 
650 0 |a Transportation  |z Alaska  |z Susitna River Region  |x Planning. 
650 0 |a Highway planning  |z Alaska  |z Susitna River Region. 
650 0 |a Roads  |z Alaska  |z Susitna River Region  |x Design and construction. 
650 0 |a Route surveying  |z Alaska  |z Susitna River Region. 
710 2 |a HARZA-EBASCO Susitna Joint Venture. 
710 2 |a Alaska Power Authority. 
830 0 |a Document (Susitna Hydroelectric Project) ;  |v no. 500. 
856 4 1 |u https://www.arlis.org/docs/vol1/Susitna/5/APA500.pdf  |z ARLIS Document Server 
901 |a ARLIS  |c orig 201409 
596 |a 9 10 
098 |a APA 00500