Consultants Meeting /

This document represents a meeting presentation. It outlines construction details on the Watana Dam and Devil Canyon Dam, required and planned activities, and updated information on the Susitna Hydroelectric Project, and contains short reports, charts, maps, and technical drawings.

Saved in:
Bibliographic Details
Alternate Title:Caption title on agenda page: Susitna Hydroelectric Project, External Review Panel, Meeting on Staged Construction : April 15 and 16, 1985, Sixth Floor Conference Room

Susitna Hydroelectric Project. Consultants Meeting
Corporate Author: Susitna Hydroelectric Project. External Review Panel. Meeting on Staged Construction (1985 : Anchorage, Alaska)
Corporate Contributor(s):HARZA-EBASCO Susitna Joint Venture.

Alaska Power Authority.
Publisher:Alaska Power Authority,
Report Numbers:APA 2653
Series:Document (Susitna Hydroelectric Project) ; no. 2653.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
LEADER 02570cam a2200481Ia 4500
001 2048204
003 SIRSI
005 20140724173539.0
007 ta
007 cr bn||a||||||
008 140724s1985 akuabde s100 0 eng d
040 |a RLA  |c RLA 
035 |a (OCoLC)884522811 
043 |a n-us-ak 
050 4 |a TK1425.S8  |b A23 no. 2653 
088 |a APA 2653 
110 2 |a Susitna Hydroelectric Project.  |b External Review Panel.  |b Meeting on Staged Construction  |d (1985 :  |c Anchorage, Alaska) 
245 1 0 |a Consultants Meeting /  |c Harza-Ebasco Susitna Joint Venture. 
246 1 |i Caption title on agenda page:  |a Susitna Hydroelectric Project, External Review Panel, Meeting on Staged Construction :  |b April 15 and 16, 1985, Sixth Floor Conference Room 
246 3 |a Susitna Hydroelectric Project.  |p Consultants Meeting 
260 |a [Anchorage, Alaska] :  |b Alaska Power Authority,  |c [1985] 
300 |a [120] p. :  |b ill., charts, maps, plans ;  |c 28 cm. 
336 |a text  |b txt  |2 rdacontent 
337 |a unmediated  |b n  |2 rdamedia 
338 |a volume  |b nc  |2 rdacarrier 
490 1 |a Document ;  |v no. 2653 
500 |a At head of title: Susitna Hydroelectric Project. 
500 |a "April 15, 1985." 
530 |a Available also in electronic format on the Internet. 
500 |a The place of the meeting is not given, but it probably coincided with the Engineering Sub-Panel Meeting held April 16, 1985 in Anchorage. 
500 |a Cataloging based on copy with incomplete chart of construction schedule (sheets 1 and 2 at the end) due to improper microfilming of original document. 
520 |a This document represents a meeting presentation. It outlines construction details on the Watana Dam and Devil Canyon Dam, required and planned activities, and updated information on the Susitna Hydroelectric Project, and contains short reports, charts, maps, and technical drawings. 
610 2 0 |a Susitna Hydroelectric Project  |v Congresses. 
650 0 |a Hydroelectric power plants  |z Alaska  |z Susitna River  |x Design and construction  |v Congresses. 
650 0 |a Dams  |z Alaska  |z Susitna River  |x Design and construction  |v Congresses. 
651 0 |a Susitna River (Alaska)  |x Power utilization  |v Congresses. 
710 2 |a HARZA-EBASCO Susitna Joint Venture. 
710 2 |a Alaska Power Authority. 
830 0 |a Document (Susitna Hydroelectric Project) ;  |v no. 2653. 
856 4 1 |u https://www.arlis.org/docs/vol1/Susitna/26/APA2653.pdf  |z Sheets 1 and 2 at end of document are incomplete.  |z ARLIS Document Server 
901 |a 3755  |c orig 
596 |a 9 10 
098 |a APA 02653