Task 1 - seismic setting review, Susitna Hydroelectric Project /

The memorandum from Scher is a seismic hazard analysis for the dams proposed at the Susitna Hydroelectric Project site. It summarizes opinions of the report "Final report on seismic studies for Susitna Hydroelectric Project" prepared by Woodward-Clyde Consultants for Acres American Incorpo...

Full description

Saved in:
Bibliographic Details
Alternate Title:Seismic setting review, Susitna Hydroelectric Project

Running title of first memorandum: Seismic setting Watana Dam site, Susitna Hydroelectric Project

Title on the Alaska Energy Authority webpage for this collection of memorandums: Susitna seismic geologic review

Geologic and geotechnical data reports review, Susitna Hydroelectric Project.
Main Author: Scher, Bob,
Additional Author(s):Magee, John

Riddle, Charles.
Corporate Contributor(s):R & M Consultants.

Alaska Energy Authority.
Publisher:Alaska Energy Authority,
Report Numbers:SuWa 220
Series:Susitna-Watana Hydroelectric Project document ; no. 220.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
Description
Summary:The memorandum from Scher is a seismic hazard analysis for the dams proposed at the Susitna Hydroelectric Project site. It summarizes opinions of the report "Final report on seismic studies for Susitna Hydroelectric Project" prepared by Woodward-Clyde Consultants for Acres American Incorporated in 1982 relative to hazards that should be considered, the current understanding of seismicity in Southcentral Alaska, and the present state-of-practice for evaluating such hazards. (That report is numbered APA 1255-1256 and 1434.) The memorandum from Riddle consists of excerpts from "Before the Federal Energy Regulatory Commission, application for license for major project, Susitna Hydroelectric Project draft license application," volume 12 : Exhibit E, Chapter 6, Geological and soil resources, released in 1985. (That volume is numbered APA 3436 and SUS 579.) The excerpted pages (E-6-2-11 to 16 ; E-6-3-4 ; E-6-3-11 ; and E-6-4-2 to 4) cover geology of the proposed Watana Dam site.
Physical Description:7, [9], 6 p. : 5 col. ill. ; 28 cm.
Notes:Title from subject lines.

Letterhead on first memorandum: R&M Consultants, Inc., Geotechnical memorandum.

A collection of two memorandums from R & M Consultants, Inc. that the Alaska Energy Authority has released Susitna-Watana Hydroelectric Project.

The first memorandum is from Bob Scher, Senior Geotechnical Engineer, to John Magee, Project Manager, dated "2 July 2009."

The second memorandum is from Charles Riddle to John Magee, both of R & M Consultants, dated "June 4, 2009."

Letterhead on second memorandum: R&M Consultants, Inc., Memorandum.

First memorandum: "R&M No. 1158.21."

Second memorandum: "1158.21."

ARLIS assigned report number: SuWa 220.

Posted on the Alaska Energy Authority's "Railbelt large hydro reports" webpage; available as of June 16, 2014.