Unit prices - backup calculations, Watana Dam, breakdown of equipment costs.

A collection of hand completed worksheets (called 'Calculations') from Acres American Incorporated regarding estimated construction equipment costs for the Susitna Hydroelectric Project. These sheets cover cofferdams, rip-rap, excavation of overburden, reusable rock, and rock waste.

Saved in:
Bibliographic Details
Alternate Title:Book H. Unit prices - backup calculations, Watana Dam, breakdown of equipment costs.

(H). Unit prices - backup calculations, Watana Dam, breakdown of equipment costs
Corporate Contributor(s):Acres American Incorporated.

HARZA-EBASCO Susitna Joint Venture.
Publisher:Acres American Incorporated,
Report Numbers:APA 106
Series:Document (Susitna Hydroelectric Project) ; no. 106.
Subjects:
Online Access:Link to Full Text
Library Holdings:Print Versions
Description
Summary:A collection of hand completed worksheets (called 'Calculations') from Acres American Incorporated regarding estimated construction equipment costs for the Susitna Hydroelectric Project. These sheets cover cofferdams, rip-rap, excavation of overburden, reusable rock, and rock waste.
Physical Description:16 p. ; 28 cm.
Notes:At head of title: (H).

Series statement from label on title page.

This document belongs to a set of volumes issued by Acres American Incorporated (as indicated in the Susitna Hydroelectric Project document index) that are also called 'Books', such as Book A, Book B, etc.

Cataloging based on copy with no page numbered 1 (perhaps the title page) or 2.