Aquatic resources study within the access alignment, transmission alignment, and construction area, Study plan Section 9.13, Initial Study Report /
Construction and operation of the proposed Susitna-Watana Hydroelectric Project requires temporary and permanent infrastructure (access roads, transmission lines, airports, and construction sites). The objectives of this study are to characterize the aquatic habitats and fish assemblages at potentia...
Saved in:
Alternate Title: | Initial Study Report. Study plan Section 9.13, Aquatic resources study within the access alignment, transmission alignment, and construction area. Draft. Initial Study Report. Aquatic resources study within the access alignment, transmission alignment, and construction area (9.13) |
---|---|
Corporate Contributor(s): | Alaska Energy Authority. R2 Resource Consultants. Susitna-Watana Hydroelectric Project. |
Publisher: | Alaska Energy Authority, |
Report Numbers: | SuWa 207 |
Edition: | Draft. |
Series: | Susitna-Watana Hydroelectric Project document ;
no. 207. |
Subjects: | |
Online Access: | Link to Full Text Link to Full Text |
Library Holdings: | Print Versions |
Summary: | Construction and operation of the proposed Susitna-Watana Hydroelectric Project requires temporary and permanent infrastructure (access roads, transmission lines, airports, and construction sites). The objectives of this study are to characterize the aquatic habitats and fish assemblages at potential stream crossings along proposed access road and transmission line alignments and to describe aquatic habitats and species present within the construction area for the dam and related hydropower facilities. The study area includes lakes and streams within a 200-meter (650-foot) buffer zone of such infrastructure in the Susitna River and Tanana River basins. This document details Alaska Energy Authority's status in implementing the study as set forth in the FERC-approved Revised study plan and as modified by FERC's Study plan determination issued February 1, 2013. |
---|---|
Physical Description: | iv, 27 p. : col. ill., col. maps ; 28 cm. |
Notes: | "February 2014." "Susitna-Watana Hydroelectric Project (FERC No. 14241)." ARLIS assigned report number: SuWa 207. |
Report Type: | Draft Initial Study Report. |
Bibliography: | Includes bibliographical references (p. 6-7). |