Probable maximum flood (PMF) study, Study plan Section 16.5, Final study plan /
As part of the preparation for construction of the Susitna-Watana Hydroelectric Project, the stability of Project facilities need to be accessed for flood loading conditions. The general objectives of this probable maximum flood (PMF) study: (1) develop a site-specific probable maximum precipitation...
Saved in:
Alternate Title: | Final study plan. Final study plan. Probable maximum flood (PMF) study 16.5 |
---|---|
Corporate Author: | |
Corporate Contributor(s): | Susitna-Watana Hydroelectric Project. |
Publisher: | [Alaska Energy Authority], |
Report Numbers: | SuWa 200 |
Series: | Susitna-Watana Hydroelectric Project document ;
no. 200. |
Subjects: | |
Online Access: | Link to Full Text Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 03074cam a2200505Ia 4500 | ||
---|---|---|---|
001 | 2017081 | ||
003 | SIRSI | ||
005 | 20140204015310.0 | ||
007 | ta | ||
007 | cr cn||||a|||| | ||
008 | 140204s2013 akub bt s000 0 eng d | ||
035 | |a (OCoLC)869838086 | ||
040 | |a RLA |c RLA | ||
049 | |a RLAA | ||
050 | 4 | |a TK1425.S8 |b S92 no. 200 | |
088 | |a SuWa 200 | ||
110 | 2 | |a Alaska Energy Authority. | |
240 | 1 | 0 | |a Final study plan. |n Study plan Section 16.5, |p Probable maximum flood (PMF) study |
245 | 1 | 0 | |a Probable maximum flood (PMF) study, Study plan Section 16.5, Final study plan / |c Alaska Energy Authority. |
246 | 1 | 7 | |a Final study plan. |p Probable maximum flood (PMF) study 16.5 |
260 | |a [Anchorage] : |b [Alaska Energy Authority], |c [2013] | ||
300 | |a 9 p. ; |c 28 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
490 | 1 | |a Susitna-Watana Hydroelectric Project document ; |v no. 200 | |
500 | |a "July 2013." | ||
500 | |a "Susitna-Watana Hydroelectric Project (FERC No. 14241)." | ||
500 | |a ARLIS assigned report number: SuWa 200. | ||
513 | |a Final study plan. | ||
510 | 3 | |a Listed in January 2014 on the Susitna-Watana Hydroelectric Project's Document webpage under the category: Final study plan. | |
530 | |a Available also in electronic format on the Internet. | ||
520 | |a As part of the preparation for construction of the Susitna-Watana Hydroelectric Project, the stability of Project facilities need to be accessed for flood loading conditions. The general objectives of this probable maximum flood (PMF) study: (1) develop a site-specific probable maximum precipitation to be used for the derivation of the PMF including both a temporal and spatial distribution of rainfall; (2) model the runoff through the project drainage basin to produce the PMF inflow, including snowmelt considerations for the Project reservoir; (3) route the PMF inflow through the Project to obtain the PMF outflow and maximum flood elevation at the dam; and (4) use the Board of Consultants for technical review during development and performance of the site-specific studies. Geology and soils will be considered only to the extent that they affect flood runoff. Structural aspects of facilities will not be included in the PMF study. | ||
504 | |a Includes bibliographical references (p. 16.5-8 to 16.5-9). | ||
650 | 0 | |a Streamflow |x Research |z Alaska |z Susitna River. | |
650 | 0 | |a Hydrologic models |z Alaska |z Susitna River Watershed. | |
650 | 0 | |a Floods |x Research |z Alaska |z Susitna River Valley. | |
710 | 2 | |a Susitna-Watana Hydroelectric Project. | |
830 | 0 | |a Susitna-Watana Hydroelectric Project document ; |v no. 200. | |
043 | |a n-us-ak | ||
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna2/FSP/SuWa200sec16-5.pdf |3 Direct link to this document. |z ARLIS Document Server |
856 | 4 | 2 | |u https://www.arlis.org/docs/vol1/Susitna2/FSP/SuWa200.html |3 List of related Final Study Plans. |z ARLIS Document Server |
901 | |a 3755 |c orig | ||
596 | |a 9 10 | ||
098 | |a SuWa 00200 |