Task 7, Environmental. Subtask 7.04, Water resources analysis. A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River /
This report researches the question: "Will the operation of the proposed Watana and Devil Canyon hydroelectric dams on the Susitna River restrict the movement of vessels during the ice-free months downstream of these dams?"--P.3.
Saved in:
Alternate Title: | Susitna Hydroelectric Project. Task 7, Environmental. Subtask 7.04, Water resources analysis. A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River Subtask 7.04, Water resources analysis. A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River Preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River |
---|---|
Main Author: | |
Corporate Contributor(s): | Alaska. Division of Land & Water Management. Acres American Incorporated. |
Publisher: | Alaska Power Authority, |
Report Numbers: | APA 473 APA 1296 SUS 420 |
Edition: | Rev. |
Series: | Document (Susitna Hydroelectric Project) ;
no. 473. Document (Susitna Hydroelectric Project) ; no. 1296. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 03233cam a2200613Ia 4500 | ||
---|---|---|---|
001 | 1615745 | ||
003 | SIRSI | ||
005 | 20120828081911.0 | ||
007 | he bm||||b|c| | ||
007 | cr cn||||a|||| | ||
008 | 830927s1982 akua t s000 0 eng d | ||
035 | |a (Sirsi) CCL149026 | ||
035 | |a (OCoLC)41697771 | ||
040 | |a Ak |c ALK |d RLA |d ALK | ||
049 | |a ALKA | ||
088 | |a APA 473 | ||
088 | |a APA 1296 | ||
088 | |a SUS 420 | ||
090 | |a TK1425.S8 |b A23 no. 473 | ||
090 | |a TK1425.S9 |b S95 no. 7.04a | ||
100 | 1 | |a Janke, Paul. | |
245 | 1 | 0 | |a Task 7, Environmental. |n Subtask 7.04, |p Water resources analysis. |p A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River / |c prepared by Paul Janke ; prepared for Acres American Incorporated. |
246 | 3 | |a Susitna Hydroelectric Project. |n Task 7, |p Environmental. |n Subtask 7.04, |p Water resources analysis. |p A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River | |
246 | 3 | 0 | |a Subtask 7.04, |p Water resources analysis. |p A preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River |
246 | 3 | 0 | |a Preliminary analysis of potential navigational problems downstream of the proposed hydroelectric dams on the Susitna River |
250 | |a Rev. | ||
260 | |a [Anchorage, Alaska] : |b Alaska Power Authority, |c [1982] | ||
300 | |a 16 p., [15] leaves of plates : |b ill. ; |c 28 cm. | ||
490 | 1 | |a [Document ; |v no. 473, 1296] | |
500 | |a At head of title: Susitna Hydroelectric Project. | ||
500 | |a "January 6, 1982, Revised: March 5, 1982." | ||
500 | |a Assigned document nos. 473 and 1296 in Susitna Hydroelectric Project document index. | ||
500 | |a Assigned AEIDC document no. SUS 420. | ||
530 | |a Available also in microfiche format and electronic format on the Internet. | ||
510 | 3 | |a Assigned APA Document no. 473 in the Susitna Hydroelectric Project document index. Also assigned no. 1296 (duplicate entry). | |
510 | 3 | |a Assigned SUS document no. 420 in the Susitna Aquatic Impact Assessment Project bibliography. | |
520 | |a This report researches the question: "Will the operation of the proposed Watana and Devil Canyon hydroelectric dams on the Susitna River restrict the movement of vessels during the ice-free months downstream of these dams?"--P.3. | ||
610 | 2 | 0 | |a Susitna Hydroelectric Project |x Environmental aspects. |
710 | 1 | |a Alaska. |b Division of Land & Water Management. | |
650 | 0 | |a Hydroelectric power plants |x Environmental aspects |z Alaska |z Susitna River. | |
651 | 0 | |a Susitna River (Alaska) |x Navigation. | |
651 | 0 | |a Susitna River (Alaska) |x Power utilization. | |
710 | 2 | |a Acres American Incorporated. | |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 473. | |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 1296. | |
043 | |a n-us-ak | ||
596 | |a 9 10 11 23 | ||
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna/4/APA473.pdf |z ARLIS Document Server |
977 | |a o41697771 | ||
901 | |a 3755 | ||
901 | |a 0104 |c TK1424.A4S98 no.7.04 | ||
098 | |a APA 00473 | ||
098 | |a SUS 00420 | ||
098 | |a APA 01296 |