Susitna-Watana Hydroelectric Project, FERC Project no. 14241-000;
Filing of Initial Study Plan Meetings Transcripts and Additional Information in Response to October 2014 Initial Study Plan Meetings


Alaska Energy Authority
Susitna-Watana Hydroelectric Project

Published: Anchorage : Alaska Energy Authority, 2014.

November 2014.

Assigned SuWa numbers 254 to 268.

These reports (cover letter with 14 attachments) were prepared for Alaska Energy Authority for the Susitna-Watana Hydroelectric Project.


 

LINKS VIA ARLIS DOCUMENT SERVER:

SuWa NumberVolumeStudy Plan Number(s)Study Title
254Cover letter-- Susitna-Watana Hydroelectric Project, FERC Project no. 14241-000; filing of Initial Study Plan Meetings transcripts and additional information in response to October 2014 Initial Study Plan Meetings.

Title from subject line.

November 14, 2014

255Attachment A-- Initial Study Report Meetings, October 15, 2014 : Millennium Hotel, 4800 Spenard Road, Anchorage, Alaska 99517

256Attachment B-- Initial Study Report Meetings, October 16, 2014 : Millennium Hotel, 4800 Spenard Road, Anchorage, Alaska 99517

257Attachment C-- Initial Study Report Meetings, October 17, 2014 : Millennium Hotel, 4800 Spenard Road, Anchorage, Alaska 99517

258Attachment D-- Initial Study Report Meetings, October 21, 2014 : Alaska Energy Authority - board room, 813 West Northern Lights Blvd., Anchorage, Alaska 99503

259Attachment E-- Initial Study Report Meetings, October 22, 2014 : Alaska Energy Authority - board room, 813 West Northern Lights Blvd., Anchorage, Alaska 99503

260Attachment F-- Initial Study Report Meetings, October 23, 2014 : Alaska Energy Authority - board room, 813 West Northern Lights Blvd., Anchorage, Alaska 99503

261Attachment G7.7, 6.5 Glacier and runoff changes (Study 7.7) and fluvial geomorphology (Study 6.5) : assessment of the potential for changes in sediment delivery to Watana Reservoir due to glacial surges, technical memorandum
262Attachment H8.6, 6.6 Riparian instream flow (Study 8.6) and fluvial geomorphology (Study 6.6) : dam effects on downstream channel and floodplain geomorphology and riparian plant communities and ecosystems - literature review, technical memorandum
  • [Main report]
  • Appendix A.   Annotated bibliography

263Attachment I9.6a (Final Study Plan) Susitna River fish distribution and abundance implementation plan : Appendix 3, Protocol for site-specific gear type selection, version 5
264Attachment J9.5, 9.6 Fish distribution and abundance in the upper and middle/lower Susitna River (Studies 9.5 and 9.6) : draft chinook and coho salmon identification protocol
265Attachment K9.9 Characterization and mapping of aquatic habitats (9.9) : errata to Initial Study Report Part A - Appendix A, remote line mapping, 2012
266Attachment L9.9 Characterization and mapping of aquatic habitats, Study 9.9 : revised map book for 2012 remote line mapping
267Attachment M9.12 Study of fish passage barriers in the middle and upper Susitna River and Susitna tributaries (Study 9.12) : fish passage criteria, technical memorandum
  • [Main report]
  • Appendix A.   Notes from Technical Team Meeting March 19, 2014
  • Appendix B.   Presentation from Technical Team Meeting March 19, 2014

268Attachment N5.7 Mercury assessment and potential for bioaccumulation study (Study 5.7) : errata to evaluation of continued mercury monitoring beyond 2014, technical memorandum
  • Errata to evaluation of continued mercury monitoring beyond 2014 technical memorandum (originally filed September 30, 2014)
  • Mercury assessment and potential for bioaccumulation study (Study 5.7), evaluation of continued mercury monitoring beyond 2014 technical memorandum (revised per errata November 14, 2014)
  • Initial Study Report Meeting : Study 5.7, mercury assessment and potential for bioaccumulation, October 16, 2014 (revised per errata November 14, 2014)