| July 11, 2022 |
Draft supplemental EIS says Alaska LNG would not add to greenhouse gases |
| July 6, 2021 |
Energy Department orders lifecycle review of Alaska LNG emissions |
| July 27, 2020 |
FERC denies requests for rehearing of Alaska LNG approval |
| June 29, 2020 |
New estimate reduces Alaska LNG project cost, but economics still challenging |
| June 22, 2020 |
Mat-Su Borough asks FERC to reconsider Port MacKenzie for LNG plant |
| May 29, 2020 |
FERC approval gives Alaska LNG 10 years to start operations |
| May 21, 2020 |
FERC approves Alaska LNG project |
| May 13, 2020 |
AGDC looks for new sponsor to take over LNG project — or it will sell off the assets |
| March 9, 2020 |
FERC issues final EIS for Alaska project |
| January 6, 2020 |
State finishes answering questions for Alaska LNG final EIS |
| October 21, 2019 |
Mat-Su and Kenai boroughs continue arguing over project site review |
| October 9, 2019 |
Comments on draft EIS cite environmental issues, LNG terminal location |
| September 30, 2019 |
Mat-Su Borough wants another review of Port MacKenzie site |
| September 23, 2019 |
Valdez and environmental law group both ask more time to response to Draft EIS |
| July 29, 2019 |
FERC sets eight public meetings in September on draft EIS |
| July 16, 2019 |
AGDC cuts staff; Valdez complains about draft EIS; competing projects move forward |
| July 1, 2019 |
Draft EIS says LNG project could have significant environmental impacts |
| June 4, 2019 |
State answers FERC questions about Cook Inlet pipeline crossing |
| May 7, 2019 |
State nearing the end of project information owed to FERC |
| March 11, 2019 |
AGDC stays on schedule with latest batch of answers to FERC |
| February 28, 2019 |
State response timeline adds 4 months to EIS schedule |
| February 18, 2019 |
AGDC criticizes Mat-Su Borough for 'factual and legal errors' |
| February 11, 2019 |
State still owes a lot of information to FERC, but no indication of change in EIS schedule |
| January 28, 2019 |
Mat-Su Borough says AGDC analysis of Port MacKenzie is inadequate |
| January 16, 2019 |
AGDC says it needs until June to answer more of FERC's engineering questions |
| December 18, 2018 |
State will submit rest of Cook Inlet crossing information by September |
| December 18, 2018 |
FERC denies state request for cooperating agency status in EIS |
| November 27, 2018 |
State tells FERC of problems with Mat-Su Borough's proposed site at Port MacKenzie |
| November 8, 2018 |
AGDC project schedule calls for work to begin first-quarter 2020 |
| October 24, 2018 |
AGDC meets with FERC to review what's needed to stay on schedule |
| October 18, 2018 |
Mat-Su, Kenai boroughs continue sparring over LNG plant site |
| October 5, 2018 |
AGDC defends LNG site selection, calls Mat-Su claims 'baseless' |
| October 3, 2018 |
FERC sends 63 pages of questions for LNG project |
| September 18, 2018 |
Mat-Su says FERC should stop Alaska LNG review until 'fair and accurate' analysis of port site |
| September 12, 2018 |
FERC approves Kenai Borough as intervenor in Alaska LNG |
| August 31, 2018 |
FERC moves up Alaska project schedule 1 month |
| August 15, 2018 |
Kenai Borough files with FERC to defend Nikiski as LNG project site |
| July 30, 2018 |
State wants to participate in federal EIS for Alaska LNG project |
| July 23, 2018 |
AGDC says Port MacKenzie "not feasible" for LNG terminal |
| July 10, 2018 |
Army Corps adds wetlands questions to Alaska LNG work list |
| June 12, 2018 |
FERC requests additional sediment modeling work |
| April 13, 2018 |
State will answer most of FERC's questions by June; last items Aug. 1 |
| March 28, 2018 |
FERC wants project to submit more specific mitigation measures |
| March 13, 2018 |
State looks for clarification before answering some of FERC's questions |
| March 13, 2018 |
FERC sets Alaska LNG schedule, with December 2019 for final EIS |
| February 15, 2018 |
FERC advises state it is falling short in providing information for EIS |
| January 15, 2018 |
Mat-Su Borough challenges Nikiski selection for LNG plant site |
| December 21, 2017 |
State continues answering questions for environmental review |
| November 17, 2017 |
State asks FERC for 'immediate action' on environmental review |
| October 13, 2017 |
State responds to last of FERC's initial data requests; waits for EIS schedule |
| August 31, 2017 |
State still expects FERC to issue EIS schedule this fall |
| August 10, 2017 |
State advises FERC some answers will take until January 2018 |
| July 7, 2017 |
FERC sends 55-page data request to state in review of Alaska LNG |
| June 8, 2017 |
LNG market could get worse before it gets better |
| May 30, 2017 |
Alaska LNG filing attracts opponents, supporters |
| April 27, 2017 |
State corporation awaits FERC review of LNG project application |
| March 7, 2017 |
State signs on to cover costs of FERC-approved contractor for EIS |
| February 15, 2017 |
Supporters push for more consideration of Valdez LNG site |
| December 28, 2016 |
FERC sends final questions on draft reports to Alaska LNG : Federal review in holding pattern, awaiting project applicant responses |
| November 30, 2016 |
Denali Park pipeline routing waits on congressional action |
| November 22, 2016 |
FERC sends more comments, questions to Alaska LNG |
| November 15, 2016 |
FERC sends 266 pages of comments, questions to Alaska LNG |
| September 1, 2016 |
Regulators continue review of LNG project reports |
| June 28, 2016 |
Alaska LNG provides more details on project construction |
| April 26, 2016 |
Alaska LNG outlines issues for next round of resource reports |
| March 16, 2016 |
'Homeless LNG' likely to keep market oversupplied this decade |
| March 10, 2016 |
Next round of LNG project reports to FERC expected to start late spring |
| February 19, 2016 |
Weak market could delay Alaska LNG project |
| December 28, 2015 |
Alaska LNG working to answer agencies' questions |
| December 14, 2015 |
Public submits wide-ranging comments to FERC |
| October 26, 2015 |
Alaska LNG project shares information on possible highway relocation |
| October 22, 2015 |
FERC schedules 12 hearings statewide on LNG project |
| October 13, 2015 |
FERC has full workload with LNG export projects |
| October 8, 2015 |
FERC asks public what should be covered in Alaska LNG review |
| October 7, 2015 |
Hard times, hard decisions for LNG projects |
| September 16, 2015 |
LNG plant construction a huge undertaking |
| August 26, 2015 |
Cook Inlet pipeline crossing is about making the best choices |
| July 7, 2015 |
Pipeline building a choreography of coordinated steps |
| June 9, 2015 |
Tokyo Gas sees Alaska in potential LNG supply mix |
| May 29, 2015 |
Energy Department approves Alaska LNG exports |
| May 26, 2015 |
Alaska LNG reviews pipeline route with government agencies |